Steel columns and bolted rafter connections inside a pre-engineered building

What Is a Pre-Engineered Building?

A pre-engineered building (PEB) uses steel members designed to work together, fabricated in a factory and assembled on site. In a warehouse, rack positions and forklift routes help determine where columns can stand and how much clear height the roof must leave.

From Warehouse Layout to Steel Frame

Trace a loaded forklift’s route from receiving into a rack aisle before fixing the column positions. At each turn, allow for the actual truck, pallet and load. Mark the positions and weights of fixed machines on the plan for the structural engineer. If separate contractors supply the frame and foundations, agree who will issue the design reactions at each column base and when. The foundation engineer needs those forces alongside the ground investigation results to complete the design.

How the Steel Frame Carries Loads

Roof panels span between purlins, which carry their weight to the rafters. The rafters transfer it through the columns to the foundations. When wind lifts the roof, the panel fasteners transfer uplift to the purlins. Wind pressure on wall panels passes through the wall girts to the frame. In a diagonally braced building, roof and wall bracing work together to carry longitudinal wind loads down to the foundations. Mark large doors early so the engineer can position the bracing around each opening.

Roof purlins and diagonal bracing beneath the steel roof panels
The purlins span between rafters to support the roof panels. The slender rods running diagonally between connections are roof bracing.
Steel column base plate and anchor rods on a concrete foundation
Anchor rods secure the column base plate to the concrete. The foundation and steelwork teams need a common elevation reference and must check the rod positions against the holes in the plate.

Choose a Layout Around the Work

Mark the clear span you need across the building and the frame spacing along its length. Measure the spacing of interior frames from one frame centreline to the next. For forklift routes, also mark the usable width at the narrowest point, such as the gap between a rack edge and a column guard. That is the space available to the truck and its load.

Warehouses With Forklifts

Plot racks, forklift routes, loading points and the top of the highest stored load. If a column can sit within a rack line without obstructing turns or picking, mark it and request a price for that option alongside a clear-span frame. For the floor design, get the load at each rack leg from the rack supplier and loaded wheel forces from the forklift supplier.

Factories With Overhead Cranes

Mark where the crane picks up and sets down each load. Specify the required hook height above the floor, the heaviest lift and how often it occurs. Ask the crane manufacturer for maximum wheel loads, wheel spacing and horizontal forces at the rails. The engineer can then design the supports for the actual crane and its duty.

Measure the Height You Can Use

Ask each bidder to show on a section drawing exactly how eave height is measured. Then check the clear operating height from the finished floor to the lowest obstruction at each location, including rafter haunches, ducts and crane runways. In a warehouse, check both the travel route and the rack face. At the highest shelf, account for how high the load and the forklift mast will reach.

For example, a six-metre machine may need extra headroom to remove its motor from above. Ask the manufacturer how far the motor must rise to clear the machine and how much room the lifting gear needs above it. Have the structural and services teams check that space on the same section drawing before fabrication.

Compare PEB Quotes on Equal Terms

Send every bidder the same drawings and specifications. Ask each to separate included work, priced extras and items awaiting information. For a price per square metre, ask for both the total price and the area used to calculate it. Check whether each bidder counts the canopy area and includes installation to the same stage.

ScopeInformation to SupplyWhat the Bidder Should Confirm
Frame, foundations and floorColumn layout, finished floor levels, available ground data and design criteria.Separate the prices for steelwork, foundations and floor. Identify who issues column reactions and anchor layouts, and who supplies and installs the anchors. Ask for the assumptions behind any foundation allowance.
Roof and wallsTemperature-controlled areas, openings, exposure conditions and plans for rooftop solar.Specify panel and insulation types and thicknesses, coatings, flashings, gutters and where downpipes terminate. If solar is planned, state the roof load allowance and where it applies.
Cranes and building servicesCrane model, wheel loads and spacing, plus the positions and weights of suspended equipment.Separate the crane, rails, runway beams and equipment supports. Identify who coordinates the crane drawings and who checks runway beam deflection against the agreed limits.
Delivery and erectionSite access, unloading and crane positions, laydown space and working hours.Separate transport, unloading and erection costs. Identify temporary bracing, the handover milestone and anything the owner must provide.

A Worked Price Comparison

Suppose both bids use the same drawings, specification and foundation scope, and both exclude VAT. Bid A lists THB 3,000,000 plus THB 120,000 for delivery and THB 180,000 for the erection crane, bringing its total to THB 3,300,000. Bid B includes both items at THB 3,200,000. On that scope, Bid B costs THB 100,000 less. Before awarding the work, compare what each warranty covers and how long it runs.

From Drawing Approval to Handover

If a quote says “delivery within eight weeks”, establish what starts the clock, such as receipt of the purchase order or approval for fabrication. For phased deliveries, distinguish the first truck on site, the last shipment and completion of erection. Check those dates against foundation readiness and the date the machinery installers need access.

  1. Before fabrication. Have the structural and machinery teams check column positions, openings and working clearances on the same plans and sections. Record the drawing numbers and revisions released for fabrication and who can authorise later changes.
  2. Before dispatch. Compare the surveyed column lines, base levels and anchor positions with the approved drawings. Have the responsible team resolve discrepancies before scheduling erection. Confirm vehicle access, unloading points and laydown space for each shipment.
  3. During erection. Record inspections against the agreed plan, identifying the member and drawing location. For damaged coatings, record the location, the specified repair method and the inspection result after repair.
  4. At handover. Collect as-built drawings, inspection reports, maintenance instructions and warranties. List outstanding items by location, owner, due date and reinspection date. Pass recurring tasks, such as gutter cleaning, to the facilities team.

Plan for Solar and Future Expansion

Adding Rooftop Solar

At quotation stage, mark the proposed panel area, the weight of the panels and mounting system, and the maintenance route. Ask the designer to record the load allowance and the roof area it covers. Before installation, give the engineer the selected layout, weights and fixing details. The engineer can check gravity and wind loads against the original design, as-built drawings and current condition of the roof, connections, purlins and main frame.

Extending an End Wall

Mark which end will expand, the approximate extra length and the opening needed between the two spaces. Ask which end frame members, foundations and bracing already allow for the extension and which will need work. Check drainage, construction access and any loading doors that must stay open while the factory operates.

Pre-Engineered Building FAQs

Can a PEB Use Hot-Rolled Steel?

Yes. PEB describes how the building components are designed, fabricated and assembled as a system. Its main frame may use welded sections built up from plate or hot-rolled sections selected by the engineer. When comparing bids, check the column layout, usable space and scope alongside the type of steel.

When Is a Clear Span Worth the Cost?

A clear span can pay off if it adds pallet positions, gives forklifts room to turn or allows a production line to move later. Draw the operation twice, once with a clear span and once with columns along the rack lines. Compare usable storage positions and the combined frame and foundation price for both layouts.

What Do I Need for an Initial Quote?

Provide the site location, building use, a dimensioned plan, door positions and the clear height you need. Specify whether the price should cover the frame alone or also the roof, walls, foundations and erection. Include available details of cranes, suspended equipment and future solar panels. Ask bidders to list assumptions and outstanding information.

Does My Quote Cover Foundations?

Check the stated scope. Ask where foundation design, foundation construction and the floor slab appear in the price. If foundations are a separate contract, identify who supplies column reactions and anchor layouts, who provides and installs the anchors, and who surveys them before steelwork arrives.

Which Handover Records Should I Keep?

Keep the latest as-built drawings and revisions, design criteria and loads, inspection records, maintenance manuals and warranties. Keep the outstanding-work list with owners and reinspection dates. For later solar panels, suspended equipment or new openings, give the engineer these records and the proposed equipment data to check against site conditions.